Vaishnavi Vistara Construction Status


Featured Image of Vaishnavi Vistara Construction Status

Vaishnavi Vistara construction status is in the pre-launch / Expression of Interest (EOI) stage as of June 2026. K-RERA registration is Applied; the current status can be verified on the Karnataka RERA portal (rera.karnataka.gov.in). The official project launch is scheduled for 15 October 2026. On-site work starts in the weeks that follow. Possession is targeted for December 2031. This page covers the full milestone calendar, the current site status and what to expect at each build stage.

Corridor context. Vaishnavi Vistara sits on Kanakapura Road (NH-948) at Doddakallasandra, South Bangalore — distinguished by its walking-distance access (5 min) to Doddakallasandra Metro Station on the operational Namma Metro Green Line. Konanakunte Cross, Vajarahalli and Thalaghattapura stations extend along the corridor. Kempegowda International Airport is 52 km via NICE Road + NH-44. The 3.27-acre campus carries 144 residences across three towers (3B+G+18), anchored by a 12,000 sq.ft. Grand Clubhouse.

Project Status Snapshot — As of 2026

Status Item Detail
Current stagePre-launch / EOI window open
Karnataka RERAApplication in process — status: verify current status at rera.karnataka.gov.in
Official launch date15 October 2026
Site mobilisationQ3 2026 (post-launch)
Excavation + pilingQ4 2026 – Q1 2027
Foundation completionQ2 – Q3 2027
Superstructure riseQ4 2027 – 2029
Finishing works2030 – Q3 2031
Handover / possessionDecember 2031

Full Milestone Calendar

Pre-Launch (Current)

  • Karnataka RERA application filed and progressing through K-RERA Board review
  • EOI window open — refundable ₹5–6 Lakh reservation locks in the ₹13,500 / sq.ft. pre-launch rate
  • on-site sales office and model apartments open for viewing once the K-RERA number is allotted
  • Site cleared and surveyed; boundary wall and approach-road work commencing

Launch — 15 October 2026

  • Karnataka RERA registration number issued (target allotment)
  • Official launch on 15 October 2026 with confirmed pricing, inventory and Agreement to Sale templates
  • EOI applicants convert to formal allotment with 10% milestone payment (less EOI)
  • Bank-panel enabled for CLP disbursement (HDFC, ICICI, SBI, Axis, Kotak, PNB, Bank of Baroda, LIC Housing)

Mobilisation — Q3 2026

  • Site office and contractor camp set up
  • Survey markings and gridding finalised against the master-plan layout
  • Tree-preservation and landscape-survey work undertaken
  • Soil-testing and geotechnical reports archived

Excavation & Piling — Q4 2026 to Q1 2027

  • Two basement levels excavated for parking and utility rooms
  • Pile foundations driven for all three towers
  • Retaining-wall structure for the basement walls cast
  • Excavation milestone payment due from buyers (10% of sale consideration)

Foundation — Q2 to Q3 2027

  • Raft and pile-cap foundation cast for all three towers
  • Plinth-beam grid completed
  • First-floor slab work begins
  • Foundation milestone payment due (10%)

Superstructure Rise — Q4 2027 through 2029

  • Slab-by-slab vertical rise — approximately 1 slab every 3–4 weeks per tower
  • By end-2028: 20+ slabs cast per tower (around 60% structural completion)
  • By end-2029: Full structural rise to 3 Basements + Ground + 18 upper floors
  • Slab milestone payments billed at 1st, 10th, 20th and final slab stages

Finishing Works — 2030 to Q3 2031

  • Brickwork and internal partitions across all apartments
  • Plumbing and electrical rough-in
  • Plastering, flooring, doors, windows, fittings
  • Painting, false ceilings, kitchen modular install
  • Lift commissioning, DG and HT power, sewage treatment plant
  • Landscape and clubhouse fit-out completion
  • Brickwork and flooring/fittings milestone payments due (10% each)

Handover — December 2031

  • Occupancy Certificate (OC) obtained from BBMP
  • Snagging walkthroughs with buyers and punch-list corrections
  • Final 5% milestone payment plus statutory charges (GST, stamp duty, registration)
  • Apartment Owners' Association handover and key collection

How to Track Progress

  • Site visits: Arranged by appointment for EOI applicants and confirmed buyers once the project is launched — submit the enquiry form to schedule one.
  • Construction updates: Quarterly emailers sent to EOI applicants and booked buyers with photographs of build progress.
  • Construction status dashboard: Watch this page — milestones are updated as they're certified by the project engineer.
  • Karnataka RERA portal: Post-registration, buyers can view quarterly progress reports on the K-RERA portal under the project's registration number.

Frequently Asked Questions about Construction Status

1. What is the current status of Vaishnavi Vistara?

The project is in its pre-launch / EOI stage. Verify current K-RERA registration status at rera.karnataka.gov.in. It is verify current status at rera.karnataka.gov.in. That is ahead of the official launch on 15 October 2026.

2. When does on-site construction start?

Active site mobilisation begins in Q3 2026 immediately after the official launch. Excavation and piling for all three towers run from Q4 2026 through Q1 2027.

3. When will the towers reach full height?

All three towers are scheduled to reach their full 3 Basements + Ground + 18 upper floor structural height by end of 2029. Finishing works run from 2030 through Q3 2031.

4. When is handover scheduled?

Handover and possession are targeted for December 2031, after the Occupancy Certificate is obtained from BBMP and snagging walkthroughs are complete.

5. Can I visit the site during construction?

Once the project is launched, EOI applicants and booked buyers can schedule a site visit by appointment through our team. Once on-site construction begins, the site office will include a viewing deck over the active build zone.

6. How are construction-linked payments triggered?

Each milestone payment is triggered when the corresponding stage is certified complete by the project engineer. Buyers receive an invoice along with the engineer's certification document. The milestone schedule is detailed on the payment-plan page.